Installation, termination and testing of Category 5e, 6 and multi-mode
fiber optic cabling throughout the news-room. This installation was
performed in a occupied office environment without disruptions
to normal business operations. The duration of this project was
approximately 3 months.
Service contract performing repairs on underground communication
infrastructure, water line and
drainage.
Installation, termination and testing of Category 3 and 5e voice-data
cabling. This installation was performed in a new warehouse environment
with aggressive project timelines. The total duration of this
project was approximately 2 months.
Excavation and placement of a new conduit system to support communication
facilities for a new dormitory campus environment. This installation
consisted of over 20,000 feet of new conduit and multiple man-hole vault
locations. The conduit system was installed in both favorable soil
conditions and in a rock soil environment.
Installation, termination and testing of category 3 and 5e voice-data cabling
in several locations throughout the library district. In several locations
the installation occurred in historic buildings where aesthetics were of
the utmost importance.
Replacement and live cut-over of an existing long-haul single-mode fiber
optic backbone system. This project consisted of installation of new
backbone cabling through a underground conduit system and a live cut-over
of over 500 single-mode fusion splices.
Installation of underground innerduct and conduits and communication
vaults by means of open trenching, directional boring and excavation.
CCE also placed fiber optic cable, performed fusion splices and direct
fiber terminations. This project involved several unique challenges
including conduit installation at a depth of over 20 feet.
Layout of server cabinets, installation of server cabinets, racking of
servers and connection of Ethernet and power to the servers.
Trenching, directional boring and excavation of new gas line service
to existing residences in the Conifer area. CCE performed fusion
connections to both new and existing gas main line.
Excavation and exposure of existing live long haul fiber cable to cover
the cable with split steel conduit and a concrete casing.
Trenching and directional boring and placement of innerduct and fiber
cable to connect several schools within the school district.
Placement of high-pair-count copper cable in a existing duct bank.
Installation of cat 3 and cat 6 cable to approximately 300 locations
throughout the building to include a warehouse with high ceilings. We also
placed fiber-optic cable between the communication closets.
Installation of cat 5e and cat 6 cable to approximately 250 workstation