Which School Fiber Upgrades Can Fit Into Winter Break?

Kyle Brengel · Nov 18, 2026 · Leave a Comment

The gym may be the busiest building on campus the week after classes end. If the fiber link feeding it also carries the door readers, cameras and athletics office phones, the first basketball practice on Monday matters more to the cutover schedule than the first day of school in January.

For school district IT directors and facilities managers in northeast Denver, November is a good time to walk the campus together. Bring the fiber drawings and the winter activity schedule. By the end of the walk, you should be able to answer three questions:

  • Which work can the crew finish while the existing network stays live?
  • Which services need an outage?
  • Who will be on campus to confirm those services are back?

Follow one connection from building to building

Consider a high school in Commerce City that wants a faster connection between the main building and a fieldhouse. Start in the main network room. Have IT identify the panel ports serving the fieldhouse and any spare strands recorded for that link. Then visit the fieldhouse and match the labels at the far end. A pair marked “spare” on an old drawing is a candidate for testing. IT still needs to confirm that the pair is available and that the proposed equipment can use it.

Facilities can fill in details that seldom make the fiber drawing. Does the fieldhouse closet open onto a room the coaches keep locked? Was the original handhole covered when the sidewalk was widened? Does either building feed another campus facility? Write the answers on one marked-up drawing. It gives the contractor a defined route to price and gives IT a list of people to call before scheduling an interruption.  This is essential for planning the bore path for any new spans.

Walk the route with the person who maintains it

On a clear November afternoon, the handhole between the gym and the parking lot may be easy to spot. Ask the grounds supervisor where the snow from that lot goes. If the answer is “right here,” mark a different staging area on the plow map and photograph the handhole from a fixed landmark. That gives the holiday crew a way to find it after a storm.

Bring last winter’s work orders on the walk. A cracked lid at the fieldhouse or a frame that has settled beside the bus loop deserves a closer look even while the fiber is carrying traffic. For each repair, record the location, who will handle it and when they can get access. If the bus loop will be empty during break, facilities may be able to schedule a frame repair there while IT keeps the building online. Confirm that with the contractor before booking either crew.

Choose the work that fits the window

What the campus walk turns upWhat to schedule
Spare fibers connect the right two rooms.Confirm strand assignments, test the fibers and stage compatible equipment before break. Reserve the outage for moving the connection and checking service.
The buildings share conduit, but the job needs a new cable.Verify the pathway, access points and space for the cable. Schedule the pull, terminations and testing ahead of the cutover wherever access allows.
The route needs a new crossing under a drive or sidewalk.Scope the underground work separately. Account for utility locating, approvals, site access and surface restoration before promising a date to IT.

A new crossing at a Brighton campus might occupy the same drive that facilities crews need for snow removal. Walking that drive with the grounds supervisor in November can settle where equipment can stand and whether the crossing belongs on the December schedule. Even if civil work carries into spring, the district can use the break to prepare the network rooms and verify the existing fiber.

CC&E conducting network upgrades in Colorado winter conditions

Give the cutover a finish line

Set two times with the district before moving a live connection. The first is the approved start. The second is the latest time IT can decide to return to the original connection and still have the building ready for its next scheduled use. Agree on how to restore the original service, who can make that call and how the team will reach that person during break.

The contractor and the district each have something to verify. The fiber crew can test the installed strands, record the results and confirm the panel labels at both ends. District IT can then check the services that use the link. At the fieldhouse, that might mean placing a call from the athletics office, having an authorized employee try the exterior badge reader and asking security to confirm that the camera feed has returned. Put a name next to each check while everyone is still available in November.

Hand the district a record it can use in January

If the fieldhouse loses connectivity next semester, the district technician should be able to open the closeout package and identify the building, panel, port and strand at each end. Ask for the updated drawing, labeled panel photos and fiber test results tied to those identifiers. Record which strands remain available for the next project. If the crew discovered a blocked conduit, mark where it stopped so the next estimator can account for it.

Before holiday coverage starts, give the on-call technician a copy they can reach if the campus network is down. Include the after-hours contact who can open the gate and network rooms, the person authorized to call in a repair crew, and any handhole repairs still open. A quick way to check the handoff is to ask the weekend technician how they would get a splicer from the parking lot to the fieldhouse panel on a snowy Saturday.

Communication Construction & Engineering works with Colorado schools on campus backbone fiber, inside-building cabling, splicing and testing. From our Denver office, we can help IT and facilities teams in Commerce City, Brighton and across the Front Range work out what can be built ahead of break and what needs a scheduled outage.

Have two buildings in mind? Send us their names, your available work dates and any fiber or conduit drawings you have. Contact CC&E to plan your school fiber upgrade.

Blog education network, network upgrade, overpull, school district, school district fiber, school ISP, school OSP, splicing

Reader Interactions

Leave a Reply

Your email address will not be published. Required fields are marked *

Let's Build Your Next Project.

✓ Underground Utilities
✓ Fiber Optic Construction
✓ Electrical Infrastructure
Request a Quote

Proudly building the infrastructure that keeps Colorado connected.

©2026 Communication Construction & Engineering LLC • All rights reserved